Build One Equipment Standard and a Sheet for Each Site
Get a record for each location before you commit the fleet order. Headquarters can specify the water types, equipment configuration, drawing revision and handover checks. Ask a person at each site to confirm the busiest service window, measured water supply, drain location, power, ventilation and the space to install and service the unit. Leave room on the sheet for photos, the shutoff location, permissions, a work window and the person who can approve it.
In a supplier interview published in 2022, Delen Private Bank’s facility manager described fitting the kitchenettes and canteen at its Antwerp head office. He intended to specify the water points in new locations and work through existing buildings gradually. For your own sites, put new fitouts and retrofits in separate groups before choosing where to pilot.
Put the Standard Through a Retrofit
Say there are five locations. A is a new fitout with utilities ready. B is an operating café where the proposed mounting area is 38 mm thick. Put both in the pilot. A will tell you how the standard works when the site is prepared. B will tell you which parts of it survive in a counter you did not design.
For a Bestware G1DS-123 configuration as shown in the manual, the tap limit is 40 mm and the side drip-tray limit is 36 mm. At B, 38 mm clears the tap’s thickness check and exceeds the side tray’s limit. Pause B’s fitting at that position. Have the installer measure the rest of the proposed area and submit a tray position and drain route that work with the drawing. Test the approved layout at B before including it in the rollout.
Separate Ready-to-Install From Ready-to-Serve
Before installation, the project lead checks each site’s utility and access record and releases the work in writing. The installer fits the unit and records the checks. Before opening to customers, the site lead watches the leak check and the agreed service test to confirm the staff can serve the specified water types. Log repeated pours under the site’s planned busy conditions, including volume and elapsed time and, if part of your requirement, the temperature and recovery to the agreed band. Ask the buyer to sign off the shared detail after both pilot sites meet their criteria.
In the five-site example, schedule C and D after the pilots pass and the two sites’ own utility or access holds are cleared. E still needs approval for the drain, so it keeps its current drinking-water service and stays off this installation list. Keep the existing drinking-water service at each conversion site available, or have an agreed fallback there, through the cutover and until local acceptance.
Leave the Site Able to Run the Equipment on Its Own
File the installed model and serial number with installation photos, the drawing revision, the agreed tests and any open defects. Train the staff on the actual unit, including who checks filters and CO₂ where applicable, what to do if a water type is unavailable, and who takes the first service call. Assign an owner and due date to each unresolved item, and hold release if it blocks safe operation or the agreed service. Use that same record to fix the detail before the next order, so the installer at the next location gets the approved version.
Sources for This Edition
- Delen Private Bank — Supplier Interview With Facility Manager Evert Saladin · Published 7 November 2022. Sustainable entrepreneurship, paragraphs on installed kitchenettes and canteen at the Antwerp head office, then intent to add units in new locations and gradually in existing buildings. The interview reports a plan at publication.
- Chris Matt, FacilitiesNet — Plumbing Retrofits Start with Fixture Inventory · Posted 9 November 2009. In the opening Rutgers case, facilities director Michael Duclos describes inventorying equipment across 134 buildings before buying fixtures in 2005. This is a reported plumbing retrofit example and an inventory principle.
- GSA Commissioning Guide · September 2020. See the process overview and construction-phase chapters on installation verification, performance testing, issue tracking, training and handover. The method is adapted to commercial installations.
- HHS Facilities Manual, Chapter 8 — Design and Construction · Commissioning: functions and responsibilities, equipment startup verification, functional performance tests, and project review. Example framework for recording completion and ownership, not a regulation for this commercial project.
- Bestware G1DS-123 / G1DS-1023 Installation Manual, 2026 V1.2 — Side Tray · PDF page 10, step ‘1. Secure Drip Tray’, parenthesis immediately following the mounting instructions. Published maximum countertop thickness 36 mm for the drip tray under the installation scheme shown.
- Bestware G1DS-123 / G1DS-1023 Installation Manual, 2026 V1.2 — Tap · PDF page 11, step ‘2. Secure Dispenser Tap’, parenthesis immediately following the mounting instructions. Published maximum countertop thickness 40 mm for the tap under the installation scheme shown.
- Bestware — What to Check Before Signing a Water-System Handover · Same-language detailed handover checklist and recorded site tests. The target is an operating guide, not a specific contract or acceptance certificate.
- Five-Site Ordering, Pilot and Approval Example · Hypothetical A–E. A is new fitout, B a retrofit with a 38 mm worktop at the intended mounting point, C and D move forward after signed pilot and site readiness, E remains on hold pending approved drain. 38 is below the 40 mm tap ceiling and above the 36 mm side tray ceiling for the indicated diagrams. Any revised fitting and final acceptance must still be checked in person.
Continue With These Decisions
- Restaurant Sparkling Water Capacity Calculator
Estimate peak service for each restaurant.
- How to Compare Commercial Water Equipment Service Contracts
Check response times, coverage and backup water by address.